ReferenceRR/2018/1976/P
StatusWITHDRAWN     
ProposalClosure of the Mill Bridge pedestrian level crossing to both the north and south side of the railway including associated development to re-align the footpath with the construction of a new concrete walkway, river wall and a gabion basket retaining wall. Demolition of existing headwall and then re-construct. New fabricated steel vierendeel truss footbridge extending across the River Tillingham.
LocationMill Bridge - over the River Tillingham, Rye
ParishRYE
Case OfficerMr S Batchelor
Received24-07-18
Validated24-07-18
Decision By18-09-18
Decided03-09-18
AgentNetwork Rail Infrastructure Ltd. Attn: Mr Jonathan Binks First Floor, Enterprise House 167-169 Westbourne Terrace Paddington, London W2 6JY